operational research kuppi series

Complete syllabus covered for Operational Research. Conducted from October 7th to November 10th 2023

Resources

Videos

Oct 7th 2023

  • Intro to OR terminology
  • Graphical methods
  • All Slack Starting method

Oct 14th 2023

  • Big M method
  • Two Phase method
  • Dual Simplex method

Oct 21st 2023

  • Sensitivity Analysis
  • Duality of OR problems

Oct 24th 2023

  • Integer Programming
  • Mid Paper Discussion

Nov 8th 2023

  • Transportation Problem
  • Transhipment Problem

Nov 9th 2023

  • Assignment Problem
  • Project Management

Nov 10th 2023

  • Project Management continued
  • Network Analysis
Correction

I have mentioned as if the project crashes are definite units and cannot be split into parts.

But you can. In here you will assume the activity there’s a linear relationship between Extra amount spent and No. of days reduced.

So for activity B we can do

  1. 1 day reduction spending Rs 1000 more or
  2. 2 days reduction spending Rs 2000 more or
  3. 3 days reduction spending Rs 3000 more

So if you need you can reduce one day at a time for each activity and see if the constraints in the critical path are not violated.

But in terms of the question explained in the kuppi, the activity D can still be selected as an approach to do crashing within the constraints.

If doing such a step, mention that assumption and clearly say you are crashing to a certain fraction value.

CSE Batch 20 @ EXMO 2023 - 29th July 2023 - Credits to the original photographer



Need more Notes?

Here are some more lecture notes available:

  • adv ai kuppi
  • time series kuppi
  • semester 8 notes
  • fuzzy logic kuppi
  • semester 7 notes
  • human computer interaction discussion
  • semester 6 notes
  • semester 5 notes
  • theory of computing kuppi
  • semester 4 notes