operational research kuppi series
Complete syllabus covered for Operational Research. Conducted from October 7th to November 10th 2023
Resources
- Miro Board Link used for writing during kuppi.
- Complete OR Folder with
- lecture notes
- model papers
- model answers
Videos
Oct 7th 2023
- Intro to OR terminology
- Graphical methods
- All Slack Starting method
Oct 14th 2023
- Big M method
- Two Phase method
- Dual Simplex method
Oct 21st 2023
- Sensitivity Analysis
- Duality of OR problems
Oct 24th 2023
- Integer Programming
- Mid Paper Discussion
Nov 8th 2023
- Transportation Problem
- Transhipment Problem
Nov 9th 2023
- Assignment Problem
- Project Management
Nov 10th 2023
- Project Management continued
- Network Analysis
Correction
I have mentioned as if the project crashes are definite units and cannot be split into parts.
But you can. In here you will assume the activity there’s a linear relationship between Extra amount spent and No. of days reduced.
So for activity B we can do
- 1 day reduction spending Rs 1000 more or
- 2 days reduction spending Rs 2000 more or
- 3 days reduction spending Rs 3000 more
So if you need you can reduce one day at a time for each activity and see if the constraints in the critical path are not violated.
But in terms of the question explained in the kuppi, the activity D can still be selected as an approach to do crashing within the constraints.
If doing such a step, mention that assumption and clearly say you are crashing to a certain fraction value.